Production planning decides what will be made, in what quantity and by when, then commits the materials, labour and machine time to deliver it. It sits between the forecast and the shop floor: the forecast says what the market will probably want, and the production plan says what the factory is actually going to build.
ASCM, the supply chain body that also trades as APICS, describes the production plan as the overall level of planned output, "usually stated as a monthly rate for each product family". Which models get built in which week is decided one level down, in the master production schedule.
The test of any production plan is whether it is feasible. A plan that ignores capacity is a wish list, and it will be quietly rewritten on the shop floor by whoever is holding the shortage that week.
Planning or scheduling? Production planning answers what to make and how much of it. Scheduling answers which machine, which shift and in what order. Treating the two as one job is a common reason a plan cannot be executed.
Try the numbers yourself with our Level Production Strategy Calculator
What is Production Planning?
ASCM defines production planning as setting "the overall level of manufacturing output" so that planned sales can be met while the business stays profitable and keeps customer lead times competitive. It is tactical planning: it works in product families and months, not single items and days.
Its output, the production plan, is "management’s authorization" for the master scheduler to turn family totals into the master production schedule (MPS), which names specific items, quantities and dates. The MPS "is not a sales item forecast": it is what the plant will build, not what customers might buy.
Where the plan starts depends on how you sell. In make-to-stock, customer orders are filled from stock and production replenishes it, so the plan starts from a forecast. In make-to-order, the product is made after the order arrives, so the plan starts from the order book and the capacity to fill it.
What is the Importance of Production Planning?
Production planning is where the promises sales has made get tested against what the plant can physically do. Where it is done badly the symptoms are consistent: expedited freight, overtime that was never budgeted, materials bought for orders that moved, and a shop floor that has quietly stopped believing the schedule.
In supply chain terms, production planning is the supply side of sales and operations planning (S&OP). ASCM describes S&OP as a practice that "compares the demand plan with inventory levels and production capacity" and looks for the imbalances. It is held at least monthly and reviewed by management at product family level. The production plan is what comes out of that meeting.
ASCM’s SCOR model of supply chain processes files production planning under P4 Plan Transform: planning the production resources needed to meet the requirements over set time periods. If you learned SCOR as Plan, Source, Make, Deliver, it is the same process: in the 2022 revision, "Make became Transform".
Purchasing buys against that plan, and material requirements planning turns it into orders for every component. An unrealistic production plan becomes unrealistic purchasing a few weeks later.
Types of Production Planning
Two different things get called “types of production planning”, and mixing them up is the usual reason the topic feels confusing. The first is the production method: how work moves through the factory. The second is the level of planning, such as the master schedule or material requirements planning, which are stages in one hierarchy rather than alternatives. The methods come first.
Grouped by the definitions in ASCM’s dictionary, the methods come down to four, from one-off work to plants that never stop. Mass production is not a fifth: ASCM says a flow shop "is often referred to as a mass production shop".
Job or Project-Based Planning
A job shop makes items "to each customer’s specifications" on general-purpose equipment, and each job follows its own routing. Project manufacturing is the extreme case: large, often unique items built to a custom design, usually in one fixed position.
Planning here means sequencing jobs through shared machines and promising dates the shop can keep. Every job is a new setup.
Batch Production Planning
In batch production, parts are "accumulated and processed together in a lot". Lots move through functional departments, and each lot may have a different routing.
The planning problem is changeovers. Every switch between products costs time, so planners group similar items and decide how big each lot should be. A furniture workshop running a batch of oak tables, then the matching chairs, is planning in batches.
Flow Production Planning
Flow production moves a standard product through the same sequence of stations without stopping. ASCM uses the word for assembly lines and process plants alike, so for planning the useful split is whether you count units or measure quantities.
Counted units on a line are repetitive manufacturing, where scheduling and control "are based on desired throughput rates" rather than work orders. The planner sets a rate per shift and protects it, so line balance and uptime matter more than sequencing. Vehicle and appliance assembly are typical.
Process or Continuous Production Planning
Continuous plants make goods that are measured rather than counted; ASCM’s examples are gasoline, steel, fertilizer, glass, and paper. The routing is fixed and setups are seldom changed.
Output varies by grade instead of by model, and a shutdown is expensive enough that planners will accept building stock they do not yet need in order to avoid one. Yield, not unit count, is the number that matters.
Not all process manufacturing runs continuously. NIST separates continuous processes from batch processes, which have “a distinct start and end”, and lists food, beverage and biotech manufacturing as typical batch work. Those plants are planned like the batch production above.
| Method and examples | Volume and variety | What the planner fights |
|---|---|---|
| Job or project Custom machinery, prototypes | One-off, to the customer’s design | Sequencing and due dates |
| Batch Bakery, paint, apparel | Lots of similar items | Changeovers and lot sizes |
| Flow (repetitive) Vehicles, appliances | High volume, few variants | Line balance and uptime |
| Continuous process Steel, glass, paper | Very high, measured not counted | Yield; the cost of stopping |
Which row you sit in decides which planning problem you actually have. Advice written for one row is often useless in another.
The diagram names three of these methods on the left and, on the right, the planning levels that every method uses.
The Production Planning Hierarchy
The terms in this table are not competing methods. They are levels of one hierarchy, usually called manufacturing planning and control, and each level takes the output of the one above it and adds detail. Planning at the top is aggregate and long range; by the bottom it is a specific job on a specific machine this afternoon.
| Level | Planning unit | Horizon | The question it answers |
|---|---|---|---|
| Sales and operations planning (the production plan) | Product families, by month | Long enough to add capacity and support the annual business plan | How much will we make in total, and can we resource it |
| Master production schedule | Specific items, by week | At least the cumulative lead time | What exactly are we building, and when |
| Rough cut capacity planning | Key resources only | Same as the master schedule | Is that schedule feasible |
| Material requirements planning | Components, from the bill of materials | Driven by the master schedule | What must we buy and make to support it |
| Capacity requirements planning | Work centres, in hours | Open and planned orders | Does each work centre have the hours |
| Shop floor control | Jobs, machines, shifts | Days and hours | What runs next on this machine |
ASCM gives a rule rather than a number for these horizons. A master schedule should cover "a minimum of cumulative lead time plus time for lot sizing", plus time to change capacity. Cumulative lead time is the longest path through the bill of materials, added end to end.
Longer plans must look far enough ahead "to permit any needed additions to capacity". A plant whose longest component path takes 14 weeks cannot run a six-week master schedule, whatever the software default says.
At the aggregate level there is also a choice about how to absorb demand that moves through the year. A level production strategy holds output steady and lets inventory rise and fall. A chase production strategy moves output up and down to track demand. Most plants land between the two, a hybrid worked through with costs in our aggregate planning example.
Steps to Create a Production Plan/Process Flow
Here is one plan followed through every step, for a factory that assembles two office chairs: a task chair and an executive chair. Each step uses the numbers from the step before, so you can check every figure.
1. Forecast Demand for the Product Family
Plan the family first, in months. The forecast for all chairs over the next six months is 1,600, 1,800, 2,400, 2,600, 2,000 and 1,600: 12,000 in total, peaking in months 3 and 4. Sales expect 75% task chairs and 25% executive chairs.
2. Set the Production Plan
There are 500 chairs in stock today, and the plant wants 500 left at the end as a buffer. Production over the six months is:
Production needed = forecast + target closing stock − opening stock
= 12,000 + 500 − 500 = 12,000 chairs
A level plan builds the same quantity every month: 12,000 ÷ 6 = 2,000 chairs. Each month’s closing stock is the opening stock plus production minus the forecast.
| Month | Forecast | Production | Closing stock |
|---|---|---|---|
| 1 | 1,600 | 2,000 | 900 |
| 2 | 1,800 | 2,000 | 1,100 |
| 3 | 2,400 | 2,000 | 700 |
| 4 | 2,600 | 2,000 | 100 |
| 5 | 2,000 | 2,000 | 100 |
| 6 | 1,600 | 2,000 | 500 |
Stock builds before the peak and is spent during it. It never falls below 100, and it ends on the 500 target, so the plan works on paper. The next step decides whether it works in the factory.
3. Check Capacity Before Anyone Commits
Each chair takes 0.5 assembly hours on average: 0.4 for a task chair and 0.8 for an executive chair, at the 75/25 mix. Six assemblers working 8 hours a day for 20 days give 960 hours a month.
Hours needed = 2,000 × 0.5 = 1,000 hours a month
Load = 1,000 ÷ 960 = 104%
The plan is 40 hours a month short. That is a decision for the planning meeting, not the shop floor: approve about 10 overtime hours a week, or hire a seventh assembler (1,120 hours, an 89% load). This plant approves the overtime.
To repeat this check on your own numbers, our capacity planning calculator gives the hours available (20 days × 8 hours × 6 people = 960). The rough cut capacity planning calculator then turns units and hours per unit into a load, four periods at a time.
A chase plan, building each month’s forecast, would need 1,300 hours in month 4, a 135% load. That gap is why this plant levels. Our capacity planning guide covers the other ways to close a capacity gap, from extra shifts to subcontracting.
4. Break the Plan into a Master Production Schedule
Month 1’s 2,000 chairs now become specific models in specific weeks. At the 75/25 mix that is 1,500 task chairs and 500 executive chairs. ASCM’s rule is that "the sum of the MPSs for the items within the product family must equal the production plan for that family", and 1,500 + 500 = 2,000 does.
The first draft runs the executive chairs in two batches of 250, in weeks 1 and 3, to save changeovers.
5. Check the Schedule Week by Week
Weekly capacity is 240 regular hours plus the 10 approved overtime hours: 250 hours. The draft fails:
| Week | Draft (task + executive) | Hours | Load |
|---|---|---|---|
| 1 | 375 + 250 | 350 | 140% |
| 2 | 375 + 0 | 150 | 60% |
| 3 | 375 + 250 | 350 | 140% |
| 4 | 375 + 0 | 150 | 60% |
The month still adds up to exactly 1,000 hours, yet two weeks are impossible. Catching that is the job of rough cut capacity planning, which ASCM says "assists the master scheduler in establishing a feasible MPS".
The fix is to build 125 executive chairs every week. Each week then needs 375 × 0.4 + 125 × 0.8 = 250 hours, a 100% load. It costs two extra changeovers a month, and a week at 100% has no slack: one absent assembler breaks it. That risk is the case for the seventh assembler.
6. Plan the Materials (MRP)
Every chair needs one gas lift cylinder, so the revised schedule needs 500 a week. There are 700 in stock, 600 more are due in week 2 on an open order, and the supplier’s lead time is 2 weeks.
| Gas lift cylinders | Week 1 | Week 2 | Week 3 | Week 4 |
|---|---|---|---|---|
| Gross requirement | 500 | 500 | 500 | 500 |
| Scheduled receipt | 0 | 600 | 0 | 0 |
| Projected on hand | 200 | 300 | 0 | 0 |
| Net requirement | 0 | 0 | 200 | 500 |
| Planned order release | 200 | 500 | 0 | 0 |
The 200 needed in week 3 must be ordered in week 1, two weeks ahead, and the 500 for week 4 in week 2. That is the kind of message MRP exists to produce: it "makes recommendations to release replenishment orders for material". Repeat it for every component in the bill of materials and you have the purchasing plan.
7. Release, Schedule and Report Back
Capacity requirements planning then turns open and planned orders into "hours of work by work center by time period", using each item’s routing. The scheduler sequences each week on the line, and the nearest weeks are locked inside a frozen zone.
Actual output and scrap are then reported back. ASCM describes production reporting as a process "for providing feedback to the production schedule", so the next plan starts from the stock that really exists, not the stock that was planned.
To run step 2 in the level production strategy calculator, enter total demand 12,500: the forecast plus the 500 chairs you want left. Then enter beginning inventory 500, 6 months and 320 chairs per assembler (160 hours ÷ 0.5). It returns 2,000 a month and rounds the crew up to seven assemblers, the hiring option in step 3.
Production Planning and Control (PPC)
India’s national open university, IGNOU, teaches the subject as production planning and control (PPC). Its operations management unit treats routing as the first phase, then scheduling and dispatching, and ends with "follow-up, known as expediting". Another IGNOU unit lists twelve functions, adding materials, manpower, methods, machines, estimating, inspection, evaluating and cost control.
The textbook words map straight onto the planning levels:
| PPC function | What it means | Where it is in the example |
|---|---|---|
| Routing | "what work is to be done, where and when" | The routing that CRP uses in step 7 |
| Loading and scheduling | A timetable on the machines that keeps delivery dates | Steps 3 to 5: the capacity checks and the master schedule |
| Dispatching | "the release of orders and instructions to start production" | Step 7, shop floor control |
| Follow-up (expediting) | Chasing work after dispatch | Step 6 releases orders on time, so less needs chasing |
Indonesian factory research uses PPIC, production planning and inventory control, as the name of a department and of a section of the plant. One design project scopes a PPIC system as forecasting, the master production schedule, MRP and lot sizing, the chain worked through above.
Difference Between Production Planning and Production Scheduling
| Aspect | Production Planning | Production Scheduling |
| Definition | Provides an overview of what the company plans to produce. | Creates a detailed view of how the company will execute the production plan. |
| Focus | Outlines production targets, required resources, processes, and overall schedule. | Specifies when each step will occur and assigns workers, machinery, and other resources to specific tasks. |
| Complexity | Generally broader and less detailed. | Can be extremely complex, especially with many interdependent steps and simultaneous production of multiple products. |
| Details | Maps out operational steps and their dependencies. | Details the specific timing and resources for each production step. |
| Tools | Often involves planning software and forecasting tools. | Utilizes scheduling software to create, monitor, and adjust detailed schedules in real time. |
| Goal | To design an efficient, cost-effective production process that meets quality standards. | To ensure that the production plan is executed smoothly and efficiently on a detailed, day-to-day basis. |
| Adjustments | Provides a framework for adjustments when problems occur. | Allows for real-time monitoring and quick adjustments to address issues as they arise. |
| Scope | Covers long-term production strategy and overall workflow. | Focuses on the short-term execution of the production plan, including daily and weekly schedules. |
One thing detailed scheduling adds is protection for the near term. Schedulers lock the closest part of the schedule inside a frozen zone, where quantities and dates cannot change, so the shop floor has a stable plan to build to while later periods stay open to adjustment.
Tools
Visual Timeline Tools
Gantt charts have been used to plan production for more than a century. ASCM defines one as a chart showing "the relationship between planned performance and actual performance over time". On a machine, one bar shows capacity and another the load against it. On a job, one bar shows the schedule and another the actual progress.
The chart is named after Henry L. Gantt, who died in 1919. In his book of that year he describes "a simple chart system, which showed the comparison between promises and performances", set up at the Frankford Arsenal before the war. It was known then as the straight line chart.
Data Management Solutions
Spreadsheets are a common starting point, and the whole worked example above fits on one sheet. They strain when many items share the same machines and components, because nothing recalculates the weekly load and the material plan together.
Advanced Software Solutions
Production planning software comes in three kinds. Enterprise resource planning (ERP) suites hold the production plan, the master schedule and MRP next to purchasing and finance. Advanced planning and scheduling (APS) tools add finite capacity: ASCM describes APS as software that uses "optimization or simulation of finite capacity scheduling". Smaller manufacturing tools cover MRP for firms leaving spreadsheets.
Which system holds which level follows ISA-95, the standard for connecting business systems to the plant. Level 4, business planning and logistics, includes ERP, where the production plan, master schedule and MRP live. Level 3, manufacturing operations management, covers the manufacturing execution systems (MES) that run the shop floor.
List of production planning software
ERP suites
- SAP S/4HANA: production planning and detailed scheduling (PP/DS) is used to plan critical products that are produced on bottleneck resources.
- Microsoft Dynamics 365 Supply Chain Management: master planning "determines the supply (materials) and capacity (resources) needs". It now runs on the Planning Optimization add-in; the old built-in engine is blocked for new deployments from version 10.0.41.
- Oracle Fusion Cloud Supply Chain Planning: its Production Scheduling creates finite schedules for the shop floor.
- Odoo Manufacturing (version 20): its master production schedule "only suggests the amount of product to be replenished"; the planner still creates the orders.
Finite scheduling (APS)
- Siemens Opcenter APS, formerly known as Preactor APS until 2020.
- Asprova: finite capacity scheduling from Asprova Corporation.
- PlanetTogether, now a CAI company: finite capacity schedules with what-if scenarios.
- DELMIA Ortems (Dassault Systèmes): "purpose-built for factory-level production planning and scheduling".
Small manufacturers
- Microsoft Excel: a common starting point, and enough for the worked example on this page.
- Katana: pitched as the software "SMBs choose when they outgrow spreadsheets".
Project and work management tools (not production planning)
- Oracle Primavera P6: Oracle sells it for planning, managing, and executing projects through its construction and engineering business. It suits engineer-to-order work run as projects, not repeat production.
- SureTrak Project Manager: retired. Oracle’s lifetime support policy shows its last support ended in November 2020.
- Microsoft Project: project management software. Project Online retired on September 30, 2026; Project desktop and Planner continue.
- Adobe Workfront: Adobe positions it across the marketing lifecycle. It plans marketing and creative work, not factory output.
Most modern ERP solutions include a production planning module in them.
Outcomes
The outcomes of a better production planning process are:
- A well-organized and efficient production process
- Improved quality of the final product
- Increased productivity and efficiency
- Reduced manufacturing time
- Reduced waste and scrap
- Reduced production costs
- Increased customer satisfaction and reduced lead time.
FAQs
Why is production planning important in supply chain management?
Because the rest of the supply chain plans against it. In sales and operations planning the production plan is checked every month against the demand plan, inventory and capacity, at product family level. Material requirements planning then turns it into orders for every component, so an unrealistic production plan becomes unrealistic purchasing.
How do you plan human resources in production?
Turn the plan into hours, then into people. Hours needed = units × standard hours per unit; hours available = people × hours per day × working days. In the chair example, 2,000 chairs × 0.5 hours = 1,000 hours against 960 available, a 40-hour monthly gap closed by overtime or one more assembler. Count hours per skill, such as welding or upholstery, not just heads. Our workforce planning guide covers the longer term.
What is Production Planning and Inventory Control?
PPIC stands for production planning and inventory control: planning what to make and when, and controlling the stock of materials and finished goods the plan creates. Indonesian factory studies use it as the name of a department. One Indonesian design project scopes a PPIC system as forecasting, the master production schedule, MRP and lot sizing, the same chain as the worked example on this page.
What are some common mistakes in production planning?
Planning only in monthly totals: in the worked example the draft schedule fitted the month but loaded two weeks to 140%. Treating the forecast as the plan, when the master schedule is what the plant will build. Running a master schedule shorter than the cumulative lead time. Ignoring changeover time. And never comparing actual output with the plan, so the next plan starts from stock that is not there.
Where to Start
If you plan in a spreadsheet today, build two things before buying software: the family plan with its closing stock (step 2) and the capacity check in hours (step 3). Both fit on one sheet.
If the monthly check passes but weeks keep overloading, the master schedule is the problem, and an ERP rough cut check or a finite scheduling tool is the next step. If shortages are the problem, you need MRP, and the bill of materials and stock records it runs on have to be accurate first.
Using Google Search? Add erp-information.com as a preferred source.




