Manufacturing Resource Planning (MRP II): Example, MRP I vs II

Last updated on by Editorial Staff
Manufacturing Resource Planning (MRP II)

Manufacturing Resource Planning (MRP II) is a method for planning all the resources of a manufacturing company in one closed loop: materials, production capacity, labor and money. It extends Material Requirements Planning (MRP I) by checking every material plan against capacity, feeding shop-floor results back into the plan and expressing the plan in financial terms. Oliver Wight popularized the term in his 1981 book, MRP II.

Where MRP I answers “what materials do we need, and when,” MRP II answers the harder question: “can we actually make this plan with the capacity, people and money we have?” This guide shows the difference with a worked example, traces where the term came from, and maps the MRP II loop to the ERP systems that carry it today.

Key facts

  • MRP II = MRP I (materials) + capacity planning + shop-floor feedback + financial planning, run as a closed loop.
  • Joseph Orlicky’s book Material Requirements Planning (1975) codified MRP; Oliver Wight’s book MRP II (1981) popularized the name of its successor.
  • Gartner introduced the term ERP in 1990, presenting it as the next generation of MRP II.
  • Every modern manufacturing ERP still runs the MRP II loop: master schedule, MRP, capacity checks, execution, feedback.

What is Manufacturing Resource Planning (MRP II)?

MRP II is a planning hierarchy that turns a business plan into a schedule the factory can actually execute, and keeps checking it as reality changes. Each level is tested against the resources it needs before the next level is planned:

  1. Business plan: revenue, margin and investment targets, in money.
  2. Sales and operations planning (production plan): volumes by product family, checked against plant-level resources (resource planning).
  3. Master production schedule (MPS): what to build, in which configuration and week, checked by rough-cut capacity planning.
  4. Material requirements planning: the MPS is exploded through the bill of materials and netted against inventory to time purchase and work orders.
  5. Capacity requirements planning (CRP): the detailed load of those work orders on each work center.
  6. Execution and feedback: shop-floor control and purchasing report what actually happened, and the plan is revised.

Alongside the units, MRP II translates the plan into money: purchase commitments, inventory projections and shipment values, so finance and operations read the same numbers.

Evolution from MRP to MRP II to ERP
The three generations: MRP in the 1970s, MRP II in the 1980s and ERP from the 1990s.

Where MRP II came from

MRP II grew out of the American production and inventory control movement of the 1970s and 1980s. The milestones below are taken from library catalog records and from the organizations involved.

YearMilestoneWhy it matters
1969Oliver Wight’s consulting firm is foundedThe firm that later led the move from MRP to MRP II and to sales and operations planning
1975Joseph Orlicky publishes Material Requirements Planning (McGraw-Hill)The book that codified MRP: time-phased netting of dependent demand through the bill of materials
1977The first Oliver Wight checklistRated companies A, B, C or D on how well they actually ran the system, not just whether they owned it
1981Oliver Wight publishes MRP IIPopularizes the term manufacturing resource planning; revised in 1984 as Manufacturing Resource Planning: MRP II
1989Darryl Landvater and Christopher Gray publish MRP II Standard SystemA functional definition of what MRP II software had to do
1990Gartner introduces the term ERPPresented as the next generation of MRP II

The vision for ERP was first articulated by the Gartner Group (Wylie, 1990). […] With its roots in manufacturing, ERP was first presented as a “next-generation MRP II.”

E. Burton Swanson, Innovating with Packaged Business Software in the 1990s, UCLA Anderson School of Management, 2000

Between MRP and MRP II sat closed-loop MRP: the same material plan, but with capacity checks and shop-floor feedback added so the plan was revised as work progressed. MRP II added the financial layer on top of that loop.

MRP I vs MRP II: what is the difference?

MRP I plans materials. MRP II plans materials together with the capacity, labor and money needed to turn them into finished goods, and it revises the plan from shop-floor feedback.

MRP I (Material Requirements Planning)Closed-loop MRPMRP II (Manufacturing Resource Planning)
PlansMaterials and inventoryMaterials, checked against capacityMaterials, capacity, labor and finance
Core questionWhat to order, how much and whenCan the plant execute the material planCan we make the plan, with what capacity and at what cost
Capacity planningNot includedIncludedIncluded, from resource planning down to CRP
FinanceNot includedNot includedPlan expressed in money as well as units
FeedbackOpen loop: plan onlyClosed loopClosed loop
Period1970sBetween the two1980s
Difference between MRP I and MRP II
MRP I and MRP II as they are usually summarized. Entire organization here means the planning functions of a manufacturing company; ERP later extended the same approach to every department.

MRP II contains everything MRP I does. It wraps material planning inside a wider plan that also checks whether the factory has the capacity and the cash to carry it out. Material Requirements Planning (MRP I) explains the material calculation itself.

How MRP II works: the core components

Core modules of an MRP II system
A simplified MRP II loop. In the standard hierarchy, resource planning checks the production plan, rough-cut capacity planning checks the master schedule and capacity requirements planning checks the detailed plan.

An MRP II system is built from a few connected parts. The first three are inherited from MRP I; the rest are what make it MRP II.

  • Master production schedule (MPS): what to build and when, based on forecast and customer demand. It drives everything downstream.
  • Bill of materials (BOM): the parts, components and sub-assemblies needed for each product, with quantities.
  • Inventory status: stock on hand, on order and allocated, so demand is netted against what is already available.
  • Capacity planning: rough-cut checks on the master schedule and detailed CRP checks on work orders, flagging where the schedule will not fit. This is the piece MRP I lacked.
  • Shop-floor control: tracks jobs and progress on the production floor and reports the results back into the plan.
  • Purchasing: times purchase orders to the plan and tracks supplier delivery.
  • Financial planning: costs the plan in money, so operations and finance work from the same figures.

These components run as a loop: the MPS sets the target, MRP explodes it into materials, capacity planning tests it, the shop floor executes and reports back, and the schedule adjusts. You can size one part of that loop with our production capacity calculator.

MRP II example: one plan, one capacity problem

The example below uses invented but internally consistent numbers to show what MRP II adds to MRP I. A furniture maker must finish 200 office chairs in week 3 and 300 in week 4. Each chair needs one upholstered seat, made in house in one week, and five casters, bought with a two-week lead time. There are 50 seats and 600 casters in stock.

Step 1: the MRP I result (materials only)

ItemGross requirementOn handNet requirementLead timeOrder release
SeatsWeek 3: 200; week 4: 30050Week 3: 150; week 4: 3001 weekWeek 2: 150; week 3: 300
Casters (5 per chair)Week 3: 1,000; week 4: 1,500600Week 3: 400; week 4: 1,5002 weeksWeek 1: 400; week 2: 1,500

MRP I stops here. It assumes the upholstery shop can make 300 seats in week 3.

Step 2: the capacity check MRP II adds

Each seat takes 0.25 hours of upholstery, and the shop has two upholsterers with 35 productive hours each, so capacity is 70 hours a week. The seat orders load week 2 with 150 × 0.25 = 37.5 hours and week 3 with 300 × 0.25 = 75 hours. Week 3 is overloaded by 5 hours, or 20 seats.

Step 3: the money question

The planner has two obvious fixes. Overtime costs 5 hours × $42 = $210. Building 20 seats a week early instead means holding 20 seats worth $35 each for one extra week; at a 25% annual carrying-cost rate that is about $3.37. MRP II moves 20 seats into week 2: releases become 170 in week 2 (42.5 hours) and 280 in week 3 (70 hours), and both weeks fit.

Step 4: the loop closes

A machine breakdown means only 160 of the 170 seats are finished in week 2. The shortfall is reported back, the remaining 10 seats move into week 3, and week 3 is now loaded with 290 × 0.25 = 72.5 hours. The planner authorizes 2.5 hours of overtime ($105) rather than miss the week 4 shipment. Material plan, capacity plan and cost were reconciled in each step, which is the whole point of MRP II.

Class A MRP II: how implementations were judged

Owning MRP II software was never the measure. From the late 1970s, companies were graded on how well they actually ran the process, and the grading survives today in a broader form.

To evaluate their progress, the original Oliver Wight Checklist was created in 1977. By objectively answering the detailed questions in the latest version, the level of proficiency can be determined and categorized as A, B, C, or D.

Oliver Wight, company history

In practice the grades separated companies that ran the business from the formal plan, with data and schedules people trusted, from companies that owned the software but kept running the plant on spreadsheets and expediting. The checklist has since grown into the Oliver Wight Class A Standard for Business Excellence, which the firm says is now in its seventh edition, and its scope reaches well beyond manufacturing planning.

MRP II vs ERP

MRP II and ERP are often confused because ERP grew directly out of MRP II. The difference is scope: MRP II plans the manufacturing operation, while ERP plans the whole enterprise on one system. See Enterprise Resource Planning (ERP).

MRP IIERP
ScopeManufacturing resources and their financial planThe entire business
CoversProduction, materials, capacity, costingAll of MRP II, plus HR, sales, CRM, procurement and projects
FocusMaking the product efficientlyRunning every department on one system
RelationshipThe manufacturing coreA superset that includes MRP II

Where the MRP II loop lives in today’s ERP

Today the MRP II loop is usually sold as part of a manufacturing ERP rather than as a separate product. Two examples from the vendors’ own documentation, checked 7 October 2026:

  • Oracle NetSuite: the supply planning glossary describes the master production schedule as the set of planning numbers that drives Material Requirements Planning. Its Rough-Cut Capacity Planning report compares the capacity available at manufacturing work centers with the capacity required by work orders and planned work orders, and needs the Manufacturing Routing and Work Center and Advanced Bill of Materials features.
  • Microsoft Dynamics 365: in Supply Chain Management, master planning runs through the Planning Optimization add-in; for smaller manufacturers, Business Central has its own supply planning.

MRP II software today

Most systems that run the full MRP II loop are sold as manufacturing ERP. Names checked against the vendors’ own sites on 7 October 2026:

Benefits of MRP II

  • Realistic schedules: capacity is checked as part of planning, so the schedule reflects what the factory can actually do.
  • Lower inventory: materials are ordered to the plan rather than held as a just-in-case buffer.
  • Better capacity use: bottlenecks show up before they stall production, as in the week 3 overload above.
  • One set of numbers: operations, purchasing and finance work from the same data.
  • Faster response: the closed loop reschedules around delays and demand changes instead of letting them cascade.

Limits of MRP II, and what came after

MRP II plans with fixed lead times and checks capacity rather than scheduling it: capacity planning shows an overload, but a planner has to resolve it, as in the example above. Plans also change every time demand or supply changes, which planners call nervousness. Two later approaches respond to this: advanced planning and scheduling (APS) systems, which schedule against finite capacity, and demand-driven MRP (DDMRP), which NetSuite’s supply planning glossary describes as a formal multi-level planning and execution method for planning material needs that lets a company build more closely to market requirements. Both still sit on the MRP II data: bills of materials, routings, inventory and the master schedule.

What makes an MRP II system succeed

Critical success factors for MRP II
Critical aspects of MRP II: correct data, gathered feedback, labor planning, inventory management and room to extend the software.

MRP II is only as good as the data and discipline behind it, which is exactly what the Class A checklist tested:

  • Accurate data: bills of materials, inventory records and lead times have to be right; see data accuracy.
  • Honest feedback: the loop only works if the shop floor reports real progress and problems.
  • Realistic capacity data: machine rates and labor availability must reflect the real plant, or capacity planning gives false confidence.
  • Trust in the plan: planners and operators must run the business on the system rather than on spreadsheets alongside it.

FAQs

What does MRP II stand for?

MRP II stands for Manufacturing Resource Planning. It is an integrated method for planning all the resources of a manufacturing company, including materials, production capacity, labor and finance. The II distinguishes it from MRP I, Material Requirements Planning, which it extends.

What is the difference between MRP and MRP II?

MRP, or MRP I, plans only materials: what to order, how much and when. MRP II adds capacity planning, shop-floor feedback and financial planning, so it plans the whole manufacturing operation and checks whether the plan can actually be executed. MRP II includes everything MRP I does.

Is MRP II the same as ERP?

No. MRP II plans manufacturing resources, while ERP plans the entire enterprise. ERP grew out of MRP II: Gartner introduced the term in 1990 as the next generation of MRP II, extending the same integrated approach to HR, sales, procurement and the rest of the business.

What is closed-loop MRP?

Closed-loop MRP is the stage between MRP and MRP II. It adds capacity checks and shop-floor feedback to material planning, so progress, delays and shortages are reported back and the plan is revised. MRP II then added financial planning on top of that loop.

Who developed MRP II?

The term is most closely associated with Oliver Wight, whose book MRP II was published in 1981 and revised in 1984 as Manufacturing Resource Planning: MRP II. It built on Material Requirements Planning, codified by Joseph Orlicky in his 1975 book of that name.

What are the main inputs to MRP II?

The three core inputs are the master production schedule, the bill of materials and the inventory status records. MRP II adds capacity data, such as work center hours and routings, and cost data, so it can plan resources and money, not just materials.

How this page was checked

Checked 7 October 2026. Publication dates come from library catalog records (Open Library) for the Orlicky, Wight, and Landvater and Gray books; the Gartner origin of ERP from Swanson’s UCLA working paper; the checklist history and current edition from Oliver Wight’s own pages; ERP features from NetSuite and Microsoft documentation; and every product name from the vendor’s site. The worked example uses invented numbers chosen to be internally consistent.

Corrections in this revision: the FAQ section was not displaying, so its questions were visible only to search engines; the software list linked Microsoft to its older Dynamics GP product and listed Prodsmart, which Autodesk now sells as Fusion Operations.

Sources

Using Google Search? Add erp-information.com as a preferred source.